Valve Replacement Starting July 11, 2017

The Water Division will start work to replace valves on the water main at N. Jefferson Ave. and E. Morgan St. on Tuesday, July 11, 2017. This work will continue through July 21, 2017. The Water Division will notify homeowners when their service will be disrupted. We apologize in advance for any inconvenience. 

July 19, 2017 - Before & After. The first picture shows the old piping and valves. The second picture is new valves that have been installed. 

Valve Replacement 07.2017 1 Valve Replacement 07.2017 2

UPDATE: Line stops and valve repairs will begin on July 18, 2017.

July 11, 2017 - The crew is breaking up the road surface on E. Morgan. The exposed 6" cast iron pipe is cleaned and measured.

072017 Watermain 1 072017 Watermain 2 

 

July 11, 2017 - Next the crew starts breaking up the road on N. Jefferson. The exposed pipe is cleaned and measured. 

072017 Watermain 3 072017 Watermain 4